Immingham Renewable Fuels Terminal

Rail Loadout Silo roof structure.

Project Objective

To supply and install roof structure to top of 50m high Rail Loadout Silo in Immingham.

Gallery

  • Immingham Renewable Fuels Terminal | Fussey Engineering
  • Immingham Renewable Fuels Terminal | Fussey Engineering
  • li>Immingham Renewable Fuels Terminal | Fussey Engineering li>Immingham Renewable Fuels Terminal | Fussey Engineering

What We Did

Taking into account the height of the Silo and the safety issues involved with working at such an extreme height, we took the decision to fully assemble the steel roof structure at ground level.

We then hoisted the completed assembly in a single lift; minimising working at height to a single shift.